Minquas Fire Company Gets A New Home
A photo and journalistic view documenting the progress of building Downingtown's new Firehouse
Wednesday, December 5, 2012
Friday, November 16, 2012
Wednesday, October 31, 2012
Saturday, September 8, 2012
Tuesday, September 4, 2012
Minquas poised to start construction above ground
Footers are poured and rebar in place
Electric conduit is in place
Supplies for the Building effort
Steel is on site
Electric conduit is in place
Supplies for the Building effort
Steel is on site
Friday, August 17, 2012
Minquas Station coming out of the ground
Beginnings of the foundations are being constructed with the first few rows of block.
Many of the utilities are have been installed and are ready for the slab to be poured
Stone being rolled out on some of the interior sections of the building
Many of the utilities are have been installed and are ready for the slab to be poured
Stone being rolled out on some of the interior sections of the building
Wednesday, August 8, 2012
Beginning the Process of Remediation
all of the soil moved through this effort will be capped by some form of barrier
survey crews ready measurments |
Subscribe to: